Bridge Crew Pours It On To Overcome Flood Delays
(3rd Quarter 2008)
|
 |
|
Progress is coming along well on V&G's Corridor H bridge
job in Handy County, W. Va. |
Neither Mother Nature nor numerous change-orders have fazed
Vecellio & Grogan crews in Virginia and West Virginia.
In northeast West Virginia, floodwaters in the South Branch of
the Potomac River swept across a temporary rock causeway,
disrupting work on the final leg of steel erection on the $30.9
million Corridor H bridge. “It withstood the flooding pretty
well,” says Matt Farley, V&G’s Structure Operations Engineer.
“We had to move the cranes out and it was tough for a couple of
days, but it didn’t wash away the causeway.”
The crews worked above the water assembling deck forms on the
bridge’s 2,139 feet of structural steel. Some 5,100 cu. yds. of
concrete – 8 1/4 inches thick – is being poured in 16 segments.
Completion is expected by mid-May.
Changes Add To Site Work
In Virginia City, Va., where V&G was awarded a Dominion Virginia
Power contract while the design phase was still underway, work
is progressing well even as design changes have added to the
project scope.
“We’ve been able to achieve steady production while
accommodating the design updates that we knew would be a
significant part of this job,” said Rick Hertzer, the division’s
Chief Engineer. Changes include retaining walls and two bridges
stout enough to hold up under fully loaded, 100-ton truck
traffic.
Originally scheduled for completion in August, work is now
expected to wrap up in February.