Above: Carpenters form the bridge deck on New Hope Road bridge
during construction of Vecellio & Grogan’s US-64 project in Raleigh, NC.
The project is expected to be finished in September.
Above: Foreman Chris Harkin, also on V&Gs US-64 project,
supervises concrete deck pouring on the bridge over Crabtree Creek.
Above: A Vecellio & Grogan crew pours a bridge deck
for a new interchange at I-440 in Raleigh, NC.
The work is part of V&G’s US-64 realignment project.
More News & Photos on our US-64 and I-540 Projects
V&G Developing Site For FedEx Airport Hub In NC (July 2004)
In Greensboro, NC, V&G is developing the site for a FedEx cargo hub beside Piedmont Triad International Airport. The $20.5 million contract includes relocating a portion of Old Oak Ridge Road around the FedEx site.
V&G is also realigning Bryan Boulevard, a four-lane roadway near the FedEx site, under a separate contract valued at $44 million. It includes building a new interchange where the realigned Old Oak Ridge Road and Bryan Boulevard will meet.
Other current Vecellio & Grogan projects include:
- SR-288 in Richmond, VA Work is winding down on the project, with all bridges completed and final paving in progress. One end of the 4.5-mile, four-lane beltway extension should be open to traffic in August, with the remaining portion due to open in September.
- US-64 in Raleigh, NC Most of the bridge work should be finished by September on V&Gs $40 million US-64 realignment project, which includes a new intersection at I-440, Raleighs inner loop.
- I-540 in Raleigh, NC V&Gs second Raleigh project involves building eight miles of I-540 (outer loop). The $67 million contract is well underway, with completion scheduled for 2006.
- Lowes / Sams Club in Beckley, WV V&G is performing all site work on a 47-acre commercial project for Cranberry Development Company.